During the meeting the issues on the Plan of the Kazakh content under the 7th edition were discussed, an overview of the current situation on the project was precented, as well as an overview of the construction works at Tengiz.

In its report Tengizchevroil LLP pointed out that:

- Reconstruction of existing facilities is completed;

- The basic work on the construction site, preparation for the main processing facility is completed;

- Lining of the railways to deliver the large goods is going to be done soon;

- The construction of the first cluster wells is ongoing;

- It is necessary to obtain permission for the next important responsible construction.

Representatives of the subsoil user noted that in 2015 more than 50 contracts were awarded, and more than 40 of them awarded to contractors with predominantly Kazakh participation. Key construction contract packages will be awarded this year, which will increase the opportunities for the development of the KC in different directions. 